Project: Ritz Carlton Tunis
Location: Sidi Bou Saïd – Tunis – Tunisia
Components: 5 stars hotel
Client: AMILCAR RESIDENCE COMPANY
Design team: ACI/HBA LONDON/POLYSTUDIO
Contractor: CTE
Task All design missions & follow up
Design phase duration: 12 months
Start date design: Octobre 2012
Phase duration construction: 24 months
Start date: Décembre 2013
End date: March 2016
Total covered area: 35 000m²
Total development area: 4,5 ha
Project cost: U$ 70 millions